Key takeaways

Phases: FAT, cold tests, hot tests, performance test over an agreed period, guarantee check and acceptance certificate.

FAT → SATfactory to site
KPIsagreed in the contract
certificatefinal acceptance

Key point

Acceptance criteria (parameters, methods, load conditions, tolerances) must be written into the contract. We define them at design or bid-review stage.

Pipework of a water treatment plant
FAQ

Frequently asked questions

Answers to the questions plant managers, engineering and HSE teams ask us most often.

Request a consultation
How long is a performance test?

Typically from one to several weeks at steady state, depending on the plant.

Insights

Related services

Follow ENKIDEC on LinkedIn

Weekly insights on regulation, technologies and real projects in water, wastewater and biomethane.

Follow on LinkedIn
Next step

Do you have a plant to design, permit or bring back to performance?

Tell us about it in a 30-minute call: we will tell you where to start, which data you need and which options to compare.